Yonge and Sheppard, North York office $18,000-$19,000

Aluminum Entrance + AODA Operator, North York

Aluminum entrance pair with barrier-free operator. Push-force passed first walkthrough, inspector signed on site.

Aluminum Entrance + AODA Operator, North York before in Yonge and Sheppard Toronto install
Aluminum Entrance + AODA Operator, North York after in Yonge and Sheppard Toronto install
Before After

Kawneer medium stile pair, offset pivots, low-energy operator, bollard actuators | 13 business days from sign-off | $18,000-$19,000

The Challenge

The existing bronze aluminum entrance at a Yonge and Sheppard office building had failing pivots and no barrier-free operator. Facility operations needed the new entrance to pass an accessibility walkthrough without a second visit.

Scope

  • Kawneer medium stile entrance pair, clear anodized
  • Offset pivots and concealed overhead closer on the inactive leaf
  • Low-energy operator with bollard-mounted actuators
  • Opening force test and handover record

Our Approach

We specified a medium stile pair so the stiles could carry the operator arm and the exit device without crowding. The written spec listed actuator heights, approach clearances on both sides and the target opening force before anything was ordered.

The old pair came out and the new entrance went in over two evenings, with a temporary secure closure in between. The operator was set and force-tested before the walkthrough.

Technician testing opening force on an automatic aluminum entrance door in North York

Outcome

Push-force passed on the first walkthrough and the inspector signed on site. The building now has a single documented entrance package covering doors, hardware and operator.

"AODA push-force passed first walkthrough. Inspector signed on spot."

Marcus O. | Facility ops, Yonge and Sheppard
Written CAD spec within 2 business days. Site measure $0 first visit.

Get a Written CAD Spec Before Anything Is Ordered

Free site measure ($0 first visit). Written spec and price range within 2 business days. Install typically 7-14 business days from sign-off.

  • No verbal estimates
  • Written warranty on every leaf
  • WSIB + fully insured

Mon-Fri 8:00 AM - 6:00 PM. Emergency board-up after hours via the same line.